2021 Road Program

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

The 2021 Road Program project consists of repairs and replacements of mostly concrete pavements in the Village, along with repairs to the Village’s sanitary, storm and water systems along these roadways. The table lists the roads on which the work will take place and the work planned. The project started in late March and will continue until the end of October; however, the work on individual streets will not take the entire seven-month construction period.

Street

Limits

Work Planned

Traffic Disruptions

Contractor's Anticipated Schedule

Good Hope Road

Waukesha Avenue to railroad tracks and Good Hope Intersection
  • Concrete pavement repairs
  • Utility repairs

Lane closures With mechanical flaggers. Through traffic will be maintained, with the exception of a full closure near the railroad tracks for one week.

 May-June

Waukesha Avenue

Keystone Court to Good Hope Road

  • Concrete pavement repairs
  • Utility repairs

Lane closures With mechanical flaggers. Through traffic will be maintained. 

COMPLETED

Hi-Tech Drive

All

  • Asphalt pavement replacement and resurfacing
  • Utility repairs.

Temporary disruptions during milling and  paving.

April-June

Miller Way

All

  • Concrete pavement repairs
  • Utility repairs

Lane closures

COMPLETED

Village Drive

Sussex Road to Main Street

  • Concrete pavement repairs
  • Utility repairs

Lane closures

April-June

Sussex Road

Main Street to Silver Spring Drive, including Village Drive intersection

  • Concrete pavement replacement and repairs
  • Utility repairs

One way southbound with detour

April-July

Industrial Park

Ditch Grading: Mid-block from Village Drive south +/- 250 ft

Pond Repairs: Along Silver Spring Drive between Power Test and Nature’sPath

  • Correct flooding on lots north of Village Drive.

None

August

Silver Spring Drive

Hickory Drive to Waukesha Avenue

  • Sidewalk construction (both sides)
  • Utility repairs

Parking lane closures. Work on this segment will not begin until June.

 June-July

 

 

Resources

2021 Road ProgramProject Boundary Map